Friday, September 20, 2013

URL to upload files to PMR

While providing log files [maximo.log, Systemout.log or SystemErr] to PMR team, we can send them by replying to their email.

If the file size is more, then we can use the URL to upload files. You should be knowing the PMR number to perform this task.
It is also useful, if you cant transfer files from server. 




PMR number: <PMR number separated by comma> [XXXXX,XXX,XXX]

Upload is for:  Tivoli
Email Address: <To whom the confirmation will be send>
  

2. Upload the files to the PMR

3. Files are uploaded to this PMR, and PMR person can download them for their reference.



4. The confirmation email will be received by the uploader.

Saturday, August 17, 2013

Adding Labor Work Hours in Assignment Manager



User reports that for some of the labors the Work hours are blank for specific dates in Assignment Manager Application. 



User need to apply the Shifts for the specified duration to the Labors.

We need to follow the below steps to fill working hours for a labor
1. Open the Calendar for an Organization to which the labor belongs to.
2. Click on Select Action --> Define/Apply Shift.

 
3. In the dialog window, select a shift and Click on “Apply Shift(s)” Button.
4. Specify any range of Dates or apply the shift to entire calendar.


5. You can find the dates in Work Periods tab of calendar application.


6. The Work hours are filled for the week in the Labor list of Assignment Manager Application.